How Much Concrete Do I Need for a Slab? Work It Out in Minutes

Pouring a slab is one of those jobs where getting the maths right before you order saves real money. Order too little and the pour stops halfway, leaving a weak cold joint. Order too much and you have paid for concrete you cannot use. The good news is that the calculation itself is simple. You only need three measurements: length, width, and thickness. The formula Volume in cubic yards = Length (ft) × Width (ft) × (Thickness in inches ÷ 12) ÷ 27 The ÷ 27 step matters because there are 27 cubic feet in one cubic yard, and ready-mix concrete is sold by the cubic yard. A worked example: a 10 × 10 ft patio slab, 4 inches thick Area: 10 × 10 = 100 square feet Volume: 100 × (4 ÷ 12) = 33.33 cubic feet Cubic yards: 33.33 ÷ 27 = 1.23 cubic yards Add 10% for waste — spillage, an uneven base, and a slightly deeper spot than planned — and you should order about 1.36 cubic yards, rounded up to 1.5 if your supplier sells in half-yard steps. Bagged concrete follows the same volume. At ro...